At the site of Psirwo/Psamar footbridges in Pokot south, West Pokot. Site handed over to the contractor Westcroft. Present was PS Prof. Arch. P. Maringa, CES, Eng. H. J. Nyaanga, SDoPW staff and County Government officials. The area Chief was also present.
Past Events
Mentor-ship at a prize giving day at Kianyaga Boys
On Friday, 10th May, 2019 in Kirinyaga County, PS Maringa attended a prize giving day at Kianyaga Boys. Students and teaching staff were awarded for their good performance in different fields including those who scored A’s in 2018 KCSE.
REHABILITATION OF LAMU TERMINAL JETTY ( MANGROVE)
The site was handed over to the contractors, Dukana Investments Company Ltd on Tuesday 7th May,2019. Presents was the County Commissioner, Mr. Kanyiri, CES Eng. Nyaanga and the project team led by Eng. Mwangi. The contractor started mobilization immediately.
Kirinyaga & Embu County (NIIMS Monitoring)
President Uhuru Kenyatta on January 22, 2019, issued a directive that all Kenyans be digitally registered by the government and issued with a Huduma identification number. To meet this directive all Cabinet Secretaries and Principal Secretaries were directed to monitor the activity. In this regard, PS Paul Maringa undertook a random inspection in Kirinyaga County. […]
Supplies Branch – Successful Bidders Issued with Notification Letters
Arch S. K. Muli, Chief Architect, State Department for Public Works standing in for PS, Prof Paul Maringa giving one of the successful bidders her letter of notification at Works Building. About 1,000 bidders were to be issued with the letters on this day and a further 500 would get them the next day. Bidders […]
Proposed Sharrif Yako Footbridge
At Isiolo’s Bulapesa Ward. Proposed site for the Sharrif Yako footbridge. Present were Hon. MCA for the Bulapesa Ward Iddi Hassan, Burat Ward MCA Hon. Yarow, CES Eng. H. J. N. Nyaanga, local leaders. Bridge will be over Marire River.
Proposed Shambani footbridge brings joy
In Isiolo County. The proposed site for Shambani footbridge in Burat Ward. Present were Hon MCA Yarow for Burat, Hon. MCA for Bulapesa Hon. Idris Hassan, CES Eng. H. J. N. Nyaanga , local leaders, County Commander of Prisons Hassan Wako. Local were in the process of constructing a makeshift log bridge in anticipation of […]
Pre-tender site visit at Likoni Fish Landing site
Pre- tender site visit at Likoni Fish Landing site on 28/03/2019 led by the Chief Structural Engineer for the State Department of Public Works, Engineer Nyaanga. Proposed original site has been given to other people after a successful petition to the National Land Commission. A new site was proposed by the CEC Fisheries in Mombasa. […]
Pre-tender Site Visit
Pre- tender site visit at Likoni Fish Landing site on 28/03/2019 led by the Chief Structural Engineer for the State Department of Publuc Works, Engineer Nyaanga.Proposed original site has been given to other people after a successful petition to the National Land Commission. A new site was proposed by the CEC Fisheries in Mombasa. Scope […]
Project Highlight – Mokowe Jetty Reconstruction Project.
During the site handing over for Mokowe jetty reconstruction project. The project which will cost Kenya Shillings 599 million will have among other components; a fueling station for boats, a storeyed waiting lounge with ground level parking spaces and an access ramp alongside staircase. This jetty is located at the road terminal point into the […]